Generator FAT guide UAE
Plan a generator factory acceptance test that closes project risk.
A useful factory acceptance test confirms the approved package, exercises the functions that matter at site and leaves a clear record of results and open items. The exact checks and acceptance limits must be agreed in the contract and inspection and test plan before manufacture.
Before the test
Freeze the inspection basis and acceptance criteria
Testing without an agreed reference creates disputes rather than evidence. The latest approved technical submittal, general arrangement, bill of materials, control philosophy and inspection and test plan should be available to the manufacturer and witness team.
The procedure should identify the test instruments, calibration status, load steps, duration, data intervals, witness points and responsibility for observations. Any test that cannot be completed at the factory should be listed as a site acceptance item.
- Approved generator rating, duty, voltage and frequency
- Approved engine, alternator, controller and major auxiliaries
- Latest mechanical, electrical and interface drawings
- Defined test sequence, load steps and acceptance limits
- Witness, hold and document-review points
- Site-only tests and excluded interfaces clearly identified
Inspection
Check identity, workmanship and maintainability before operation
| Inspection area | Typical checks |
|---|---|
| Equipment identity | Nameplates, model and serial numbers, rating labels and approved component makes |
| Mechanical package | Base frame, mounts, guards, fasteners, cooling, fuel, exhaust, leaks and fluid levels |
| Enclosure or container | Dimensions, doors, seals, louvers, attenuation, lifting points, finish and access |
| Electrical work | Panel labels, cable support, terminations, earthing, batteries, chargers and auxiliary supplies |
| Maintainability | Routine-service clearances, drain points and credible access for major-component work |
| Documentation | Drawings, manuals, certificates, test forms and agreed spare-parts information |
Operating test
Exercise controls, protection and agreed load steps
The load test should follow the contract procedure for the exact generator rating and duty. A common staged sequence is useful for planning, but it is not an automatic acceptance standard and should not replace the approved procedure.
| Test stage | Evidence to record |
|---|---|
| Pre-start | Fluid levels, battery condition, emergency-stop reset, breaker state and controller readiness |
| Start and no-load | Start sequence, voltage, frequency, pressure, temperature, charging and abnormal noise or vibration |
| Staged load | kW, kVA, current by phase, voltage, frequency, power factor, temperatures and pressures at agreed intervals |
| Load changes | Transient response and recovery against the agreed project limits |
| Controls and protection | Alarms, trips, emergency stop, remote signals and automatic functions included in scope |
| Cool-down and shutdown | Unloading, cool-down timing, stop sequence, leaks, final alarms and post-test condition |
Release
Close observations and preserve traceable test records
- 01
Record
Capture readings, serial numbers, instrument details, photographs and witness attendance on controlled forms.
- 02
Classify
Separate release-blocking defects from minor items and site-dependent checks.
- 03
Correct
Assign owners and dates, complete repairs or adjustments and provide evidence of retest where needed.
- 04
Approve
Obtain the required signatures or documented release status under the project inspection plan.
- 05
Handover
Include the accepted reports, drawings, manuals and remaining site tests in the delivery record.
Frequently asked questions
Technical questions, answered clearly
Final selections and compliance are confirmed against the project specification and approved technical submittal.
What is a generator factory acceptance test?
A generator FAT is a planned inspection and test at the manufacturing facility to compare the completed package with approved documents, verify agreed functions and record operating results before dispatch.
Does every generator FAT require a load-bank test?
The test scope is contractual. Load-bank testing is commonly used to verify operation under controlled electrical load, but the required steps, duration, acceptance criteria and witness requirements must be agreed for the project.
Can a consultant witness generator testing in Dubai?
Yes. Patsons can plan customer, consultant or third-party witness points at its Dubai facility when they are included in the inspection and test plan and coordinated before production.
Does factory testing replace site acceptance testing?
No. Site testing confirms installation-dependent items such as switchgear interfaces, fuel and exhaust systems, ventilation, remote signals, automatic transfer and operation with the actual connected loads.